Just to share and document my current journey as of this moment on our family plans to move from Singapore to Australia.
Below are my timelines for this journey:
Year Month Activity
2015 January Requirements Gathering
2015 February Requirements Gathering / IELTS Review
2015 March Requirements Gathering / IELTS Review
2015 April ACS Applications / IELTS Review
2015 May IELTS Review
2015 June IELTS Exam & EOI Applications
2015 July Expected EOI Approval
2015 August " 1. Visa 189 Applications
2. Uploading of documents
3. Medical examinations
4. NBI Clearance & Police Clearance "
2015 September Forecast of Visa Approval
2015 October - service
2015 November - service
2015 December - service
2016 January Tentative plan to migrate to AU
Requirement gathering is the most tedious part aside from IELTS preparations.
I have completed gathering all the requirements only during the first week of April and have all the documents CTCed. I have a total of 8 years and 2 months experience after ACS deducted 4 years on my total working experience. Attached are total years assessed by ACS.
Unfortunately, my work experience with NCS was not considered as my former manager did not agree for statutory declaration so I ended up using same ACS format without company letterheads. I have included my manager name card (but was not able to include his company ID) but still this was not recognized by ACS.
Attached as well are the list of complete documents that I have submitted to ACS.
Highlights of our journey:
January 2015 to April 2015 - requirements gathering ( Philippines & Singapore )
06 April 2015 - CTCed all the documents ( http://www.lbllaw.com.sg/AboutUs.htm)
09 April 2015 - Launch my ACS applications for Computer Network and System Engineer.
15 April 2015 - ACS results were received.
Currently working and preparing for my IELTS examinations.