June 2013 - Started collecting documents and CTCs
July 12, 2013 - Vetassess recieved documents
July 27, 2013 - IELTS Exam with overall 7.5
Oct 18, 2013 - Vetassess online Status "Completed"
Oct 21, 2013 - Vetassess online Status "Positive"
Oct 21, 2013 - Requested Vetassess for Fax copy, recieved same day
Oct 21, 2013 - EOI Submission
Oct 22, 2013 - ACT SS Submitted Online
Oct 24, 2013 - ACT SS Acknowledge Payment Email Recieved
Nov 29, 2013 - ACT further info requested (job openings)
Dec 2, 2013 - Submitted further info requested
Dec 5, 2013 - ACT acknowledged decision received. ACT SS granted
Dec 5, 2013 - Skillselect invitation recieved to lodge 190
Dec 6, 2013 - Lodged visa 190, payment done
Dec 6, 2013 - SGPCOC requested
Dec 27, 2013 - SGPCOC obtained
Jan 3, 2014 - Front loaded all documents except medicals and form 80
Jan 6, 2014 - status of onlineimmi changed from required to recieved.
Jan 11, 2014 - finished medicals in SG, pointmedical and radlink.
Jan 14, 2014 - frontloaded form 80
Jan 16, 2014 - medicals uploaded to onlineimmi, no further info required
Jan 24, 2014 - Visa Grant, Direct Grant.